Pythian Manor - Tulsa, OK - October 2016 Update
Thursday, October 20, 2016 at 9:47 AM
There has been a lot of activity at Tulsa’s Pythian Manor! The project is on track and running smoothly. All 24 units (of 101) in the 1st phase have been painted as well as new cabinets installed and flooring. All doors will be installed by the end of this week. We have also begun installation of new plumbing fixtures as well as started the new Hardie siding!